East Road Post Phase 1

Phase 1 of Eagle Street PartnersMarshall Yards Development on, East Road has achieved PC with 211 of the 554 apartments now completed. Six are now completed with the support of Bennett (Construction) Ltd as main contractor, along with their subcontractors, and the wider design team.

Phase 1 includes the delivery of a Management Suite, Tenant Amenity space, Gym, Men’s Shed, 164 undercroft parking spaces and external podium landscaping.

A significant milestone for the project and a strong team effort across all involved.

Client Team
Eagle Street Partners
Harrison Street
DLC Europe
Cushman & Wakefield

Main Contractor
Bennett (Construction) Ltd

Design Team
Architect (Construction): JFA
Architect (Planning): O’Mahony Pike Architects
Architect (Tenant Amenities): Saul Design Architecture & Interiors
Civil and Structural: DBFL Consulting Engineers Ltd.
Mech & Elec: Ethos Engineering
Fire and DAC: Maurice Johnson & Partners
Assigned Certifier: ORS Building Consultants
PSDP: ORS Building Consultants
ESG: Ethos Engineering
Landscaping: Brady Shipman Martin
Planning : Brady Shipman Martin
QS: Linesight
Acoustics: AWN Consulting Ltd.
Roof Access Strategy: Altura Engineering Ltd.
Façade: bda – Billings Design Associates Ltd.
FF&E: MJF Interiors